Following on from the beginning of the landscape works, which started two weeks ago in the park, I’m happy to say that the building contractors will be joining them on site from next week.
Blakedown (our landscape contractors) will continue focusing on their two phases of workover the next couple of months in the sensory garden and then down by the fountain and piazza. BBS (who are our building contractors) will be arriving in the park on Monday morning and will initially be focusing on securing their compound around the existing building and establishing a safe access route into the park from the Christchurch Route entrance for heavy machines. We’ve tried our best to limit any disruption in the park while the works are ongoing but some are unavoidable. I’m pleased to confirm that we took delivery today of temporary toilets in the car park which should be available from early next week until the end of the summer months.